Subscribe for notification
Categories: Latest

Bullet Train Completion Date Depends On…: What Railways Said In RTI Reply

The Indian Railways is unable to assess the completion date of the country’s first bullet train project because all work tenders have not been awarded yet.

The National High Speed Rail Corporation Limited (NHSRCL), which is constructing the 508 km long corridor, said this in response to an application under the Right to Information Act.

Madhya Pradesh-based Chandra Shekhar Gaur sought to know if the NHSRCL is in a position to give a final date for the completion of the whole project though an application under the RTI.

Responding to the same, the NHSRCL said, “Completion date for Mumbai-Ahmedabad High Speed Rail Project (MAHSRP) can be assessed after award of all tenders/packages.” The project was launched in 2017 and initially it was scheduled to be ready by December 2023 but land acquisition issues as well as Covid delayed its progress significantly.

The Railways Ministry has officially announced the completion of the first phase, a 50-km long stretch between Surat and Bilimora, by August 2026. It also announced in January 2024 that 100 per cent land was acquired for the project.

The NHSRCL also said in response to the RTI application that rail tracks have not been laid yet, adding, however, by April 6, 2024, “a total length of 157 km viaduct has been completed”.

Providing an update on the progress work of the corridor, Union Railways Minister Ashwini Vaishnaw informed on X on March 28, 2024 that 295.5 km of pier work and 153 km of viaduct has been completed.

“Piers are big cylindrical columns erected on the ground. Girders are placed on piers to make a viaduct. On the viaduct, a reinforced concrete track bed is placed. Then comes the precast track slab on it. The rails are fitted on the track slab with the help of fastening devices,” said an expert associated with the project.

“Out of a total length of 508 km of the project, 465 km are on viaducts, 9,82 kms on bridges, 5,22 kms pass through mountain tunnels and 21km is underground with 7 km will be under the sea,” he added.

According to the NHSRCL, the bullet train will run at its maximum speed of 320 km to cover the 508 km distance in 2 hours and 58 minutes which includes its stoppage time at all 10 stations. It will start from Mumbai and terminate at Sabarmati after covering ten stations namely Thane, Virar, Boisar, Vapi, Bilimora, Surat, Bharuch, Vadodara, Anand and Ahmedabad.

“Out of 508 km, 352 km falls in Gujarat and Dadar & Nagar Haveli and remaining 156 km is in Maharashtra. There are a total 12 stations out of which 8 are in Gujarat and 4 in Maharashtra,” a project expert said, adding the estimated cost of the project is 1,08,000 crore.
 

Recent Posts

PM Modi: Culture, Cuisine, Cricket Strengthen India-Guyana Ties

Culture, cuisine and cricket deeply connect India and Guyana, Prime Minister Narendra Modi has said,…

2 hours ago

Elon Musk Slams Australia’s Plan To Ban Social Media For Kids Under 16

US billionaire Elon Musk, owner of social media platform X, has criticised Australia's proposed law…

2 hours ago

Assam Chief Minister Unveils These Facilities At Legislative Complex

Chief Minister Himanta Biswa Sarma on Thursday unveiled several newly developed facilities within the state…

3 hours ago

Assam Chief Minister Unveils These Facilities At Legislative Complex

Chief Minister Himanta Biswa Sarma on Thursday unveiled several newly developed facilities within the state…

3 hours ago

North Korea’s Kim Accuses US Of Escalating Tensions, Warns Of Nuclear War

North Korean leader Kim Jong Un has accused the United States of ramping up tension…

3 hours ago

NDMC Launches ‘Night Cleaning Drive’ Amid Delhi’s ‘Very Poor’ Air Quality

In an effort to curb pollution levels, the New Delhi Municipal Corporation (NDMC) carried out…

3 hours ago